Typical schedule
1. Requirement review & concept design: 5–10 working days; 2. Detailed design: 10–15 days; 3. Fabrication & assembly: 25–35 days; 4. In-house commissioning: 5–8 days; 5. On-site installation & acceptance: 3–7 days.
Total lead time is typically 45–70 working days depending on line scale, cycle time and infeed complexity.